Actual vs. Planned Hours in Task Type Report

Overview

Users sometimes need to see the variance of their actual and planned work required. For that purpose they can simply follow the steps below.

Details

  1. Create a new Column in a Task type Report>switch to textmode
  2. Copy and paste the code below

aggregator.function=SUM
aggregator.valueexpression=SUB({actualWork}, {workRequired})
aggregator.valueformat=compound
displayname=Hours Variance
linkedname=direct
textmode=true
valueexpression=SUB({actualWork}, {workRequired})/60
valueformat=customNumberAsString