Problem
My project status will not change from Complete back to Current. Why is this happening?
The cause of this problem is the Completion Mode setting on your project. If a project's Completion Mode is set to Automatic, then the project will automatically change the status from Current to Complete after the project's percent complete bar is 100%.
Solution
If a project's Completion Mode is set to Manual, then the project status can be changed from Current to Complete anytime.
To update a project's completion mode to Manual:
- Navigate to the project you wish to update.
- Click Edit Project on the upper-right side of the screen.
- Click Settings on the left-side of the screen.
- Locate the Completion Mode drop-down menu, and select Manual.
- Click Save Changes.
Thank you for taking the time to provide feedback. We appreciate and value your contribution to our site. Feedback provided here is regularly reviewed by our Product Documentation team. Please ensure your comments are specific to improving this help article. Any questions or requests outside this help article content should be directed to our Community User Forum or by submitting a ticket to customer support.