Follow
Understanding the Areas of the Resource Planner

 

***

The highlighted information on this page refers to functionality not yet generally available. It is available only in the Preview Sandbox environment.

By using the Resource Planner, you can easily understand the availability of your resources, as well as the planned time necessary to complete the work on your projects. You can then manage the allocation of your users and their job roles on the projects they are assigned to. You cannot manage the allocation of teams on the tasks they are assigned to in the Resource Planner. 

For more information about how to budget your resources using the Resource Planner, see "Planning in the Resource Planner."

You can find the following areas in the Resource Planner:

RP_areas_Dec._7__2017.png

Timeline of Projects

Use the calendar at the top of the Resource Planner to navigate the timeline of the projects you are viewing. The timeline starts with today's month, by default. 
For more information about changing the time frame of the timeline you are displaying in the Resource Planner, see "Time Frame Selection."

Time Frame Selection

By default, the Resource Planner shows resource information for six months at a time, starting with the current month. 

You can select from the following date range options in the Resource Planner by clicking the appropriate buttons:

  • Week to display information by week.
  • Month to display information by month.
  • Quarter to display information by quarter.
  • Today to return to today's month, week, or quarter.
  • By clicking the back and forward arrows you can move backwards and forwards on the timeline.
    time_frame_selection_in_the_resource_planner.png
    Six blocks of time display at one time in the Resource Planner.

Project/ Role/ User View Selection

You can change the view in the Resource Planner depending on how you want the information to display. When you change the view, the object hierarchy in the Resource Planner also changes. 

For more information about what columns you see in the Resource Planner depending on which view you select, see "Availability and Allocation of Resources."Your permissions to projects and tasks determine what is displayed under the names of the users you see in the View by User view.
 
The following scenarios exist: 
  • When you do not have permissions to see projects and the tasks or issues that are assigned to the users displayed in the Resource Planner, those items are listed under the Inaccessible Items sections. The Inaccessible Items sections replace the Project or Task sections in this case.
  • When you do not have permissions to see the projects, but you have access to see the tasks or issues on the projects, the projects, tasks, and issues are listed under the names of the users assigned to them.
  • When you have permissions to see the projects, but not any tasks or issues on the projects, the project name displays, and the tasks and issues are listed under the Inaccessible Items section. 
    For more information about permissions in Workfront, see "Understanding Permissions in the Access Model." inaccessible_items_in_RP_with___column_and_red_outline__1_.png
    IMPORTANT You cannot budget your resources when applying the View by User view to the Resource Planner. You must budget your resources using the View by Project or View by Role views, and use the View by User view to review your users' allocation and availability in relation to the planned work. 

To change the view in the Resource Planner:

  1. Navigate to the Resource Planner.
    For more information about accessing the Resource Planner, see the "Accessing the Resource Planner" section in "Planning in the Resource Planner."
  2. In the View by Project drop-down menu, select one of the following views:

View by Project

The Resource Planner displays the first 2000 projects for which you are the Resource Manager.
For more information about limitations when viewing the Resource Planner in the Project View, see the "Project View" section in "Understanding Limitations in Displaying Information in the Resource Planner." (take this note out after 18.2 if the limitation has been lifted). 
You can expand each project to display a list of job roles, and every job role to display a list of users that can fulfill those roles on the projects. This is the default view in the Production environment. (take this note out after 18.2 production)
The projects are listed in the order of their priority. 
For more information about project priority in the Resource Planner, see "Project Planning Priority."
When this view is applied, the Role Hours, FTE or Cost add up to the Project Hours, FTE or Cost.

resource_planner_view_by_project.png

View by Role

The Resource Planner displays a list of 2000 job roles, in alphabetical order, which are associated with projects for which you are the Resource Manager.
For more information about limitations when viewing the Resource Planner in the Role View, see the "Role View" section in "Understanding Limitations in Displaying Information in the Resource Planner."
 (remove after limitation is lifted, after 18.2)
You can expand each job role to display a list of projects where that role is assigned, and every project to display a list of users that can fulfill those roles on those projects.
The projects are listed under the job role in the same order of priority as they are listed in the Project View. 

When this view is applied, the Project Hours, FTE or Cost add up to the Role Hours, FTE or Cost.
resource_planner_view_by_role.png

View by User

You do not have to be a Resource Manager on any projects to see information in this view. You can see all the users you have permissions to View. 

You can expand each user to display a list of projects where that user is assigned, expand every project to display a list of roles that user can fulfill on those projects, then expand each role to display a list of tasks or issues the user in that role is assigned to. Completed tasks and issues also display. 
The projects are listed under the job role in the same order of priority as they are listed in the Project View. If users have no job role associated with them, the Hours or FTE values are listed under the No Role section. 

You can display a different number of users and items listed under them depending on whether you access the Resource Planner in the Production or the Preview environment. 
For more information about limitations when viewing the Resource Planner in the User View, see the "User View" section in "Understanding Limitations in Displaying Information in the Resource Planner."
When this view is applied, the Project Hours or FTE add up to the User Hours or FTE. 
resource_planner___column_for_user_view.png

Project Name

You can see the following projects in the Resource Planner:

  • Projects you are designated for as a Resource Manager.
  • Projects which are in a status that equates with one of the following:
    • Current
    • Planning
    • Approved
    • Idea
    • On Hold
    • Requested.

Project Planning Priority

Understanding Project Planning Priority is important for defining the order of the projects in the Resource Planner.

By default, the projects are listed in the Resource Planner by taking into consideration following criteria:

You can manually prioritize your projects in the Resource Planner only when you apply the View by Project view. 

If you apply the View by Role or the View by User views on the Resource Planner, the projects appear in the same order of priority established in the View by Project view.

Changing the Project Planning Priority

As a Resource Manager, you can reorder the projects in the Resource Planner by giving them a priority, when you display the Resource Planner in the View by Project view. By giving projects a new priority, you can rank them in order of importance. The priority number you give the projects in the Resource Planner is unique to you. Another Resource Manager looking at the same Resource Planner, with the same projects, might have the projects ranked by a different priority order.

You cannot report on the Project Planning Priority field. This is visible just in the Resource Planner and it serves as a flag for prioritizing your projects. 

To edit the Project Planning Priority:

  1. Navigate to the Resource Planner.
    For more information about accessing the Resource Planner, see the "Accessing the Resource Planner" section in "Planning in the Resource Planner."
  2. Click inside the field to the left of the project name which contains a number, enter a number to change Planning Priority, then click Enter.

    Or
  3.  Select one project by keeping the Command (on a Mac), or Control (on a PC) key down, then click the name of the project. Release the key on the keyboard, drag the project to a new spot and drop the project to place it in the new spot. 
    When you select numbers to prioritize projects, select lower numbers for higher (more important) priorities, and higher numbers for lower (less important) priorities. 

    If you change the priority number of a project to a lower number (higher priority), all other projects in the Resource Planner shift down on the list (become less important).
    If you change the priority number of a project to a higher number (lower priority), all other projects in the Resource Planner shift up on the list (become more important).

Understanding the Effect of Project Planning Priority on User Available Hours

The Project Planning Priority affects the Available hours of users. The users associated with the project with the highest priority show their fullest availability for the Available Hours column for this project.

The same users associated with the second project in order of priority will show an Available Hours value which is the difference between their full amount of Available Hours and what has already been budgeted for the first project in the Budgeted Hours column, and so on.  

If no hours have been budgeted for the first project (in order of priority) for a user, but hours have been budgeted for the second project for the same user, the user will show the full amount of available hours for both projects.

We recommend updating the Budgeted Hours column for your users in the order of the projects in the Resource Planner, to ensure that you can accurately see the Available Hours for the user at all times. 

NOTE Because the Project Planning Priority is unique to every Resource Manager, your second priority project might be a first priority project for another Resource Manager. If another Resource Manager budgets a resource for their first project, the Available Hours will decrease for that resource for your first project based on that change.

The Resource Manager who budgets the hours first allocates that resource and reduces the number of Available Hours for that resource across the system. The amount of Available Hours should update for all the Resource Managers as soon as the Budgeted Hours are saved for a resource in the Resource Planner.  
For more information about Available Hours, see "Availability and Allocation of Resources." 

Job Role Name

The following categories of job roles are listed in the Resource Planner: 

  • The job roles that are assigned to tasks.
  • The job roles that are not assigned to tasks, but are the primary job roles of the users associated with the Resource Pools of the projects. 
  • The secondary job roles of users who are assigned to tasks in those job roles. 
  • The secondary job roles of users who have a valid Percentage of FTE Availability in their profile. 
    For more information about the Percentage of FTE Availability for job roles, see "Editing Users."

    NOTE Job roles assigned to issues are also listed when the Include hours from Issue setting is enabled. For more information about enabling issue hours in the Resource Planner, see "Settings."

Project and Role Options

You can use the quick links inside the Options menus for projects and job roles to automatically budget allocations for your resources.

To access the Options menu for projects and job roles displayed in the Resource Planner:

  1. Navigate to the Resource Planner.
    For more information about accessing the Resource Planner, see the "Accessing the Resource Planner" section in "Planning in the Resource Planner."
    The projects for which you are a Resource Manager display in the list, by default. 
  2. (Optional) Expand each project to see a list of job roles associated with it. 
    Or
  3. (Optional) Select View by Role, then expand each role to see a list of projects associated with it. 
  4. Mouse over the name of a project or of a job role.
  5. Click the Options icon which displays to the far right of the project or role.
    options_icon_resource_planner.png
  6. Click an option to automatically specify the amount of Budgeted Hours (BDG), to access the project, or to review whether you can adjust the budgeting dates of the project.

Depending on what view you apply to the Resource Planner, the Options menus for project and job roles change. 
For more information about what displays in the Resource Planner based on the view you select, see "Project/ Role/ User View Selection." 

NOTE Some of the options might not display if some of the prerequisites of working in the Resource Planner are missing.
For example, some of the options might not display in the following scenarios:

  • When projects are not associated with Resource Pools.
  • When Resource Pools that are associated with projects do not contain users.
  • When Resource Pools that are associated with projects contain users with no job role associated with them.

The following information displays in the Options menus of projects and roles based on what view you select for the Resource Planner: 

  View by Project View by Role View by User
Project Options
  • View Project: Select this to view the project in Workfront. The project opens in a new tab.
  • Set Roles' Planned Hours as Budgeted: Select this option to make the Budgeted Hours of the role become identical to their Planned Hours. The total of the Budgeted Hours for the roles will display for the Project Budgeted Hours.
  • Adjust Budgeting Dates: Select this option to move the Budgeted Hours to a different time frame. 
    For more information about adjusting budgeting dates, see the "Adjusting Budgeted Dates" section in "Planning in the Resource Planner."
  • View ProjectSelect this to view the project in Workfront. The project opens in a new tab.
  • Set Users' Planned Hours as Budgeted: Select this option to make the Budgeted Hours of the user become identical to the their Planned Hours. 
  • Total Users' Budgeted Hours for Project: Select this option to add all the user Budgeted Hours together and display the total as the Budgeted Hours for the project. We recommend that you use this option after you have either manually budgeted your users, or you have used the previous option first. 
  • View ProjectSelect this to view the project in Workfront. The project opens in a new tab.
Role Options
  • Set Users' Planned Hours as Budgeted: Select this option to make the Budgeted Hours of the user become identical to their Planned Hours. 
  • Total Users' Budgeted Hours for Role: Select this option to add all the Budgeted Hours of the user together and display the total as the Budgeted Hours for the role. We recommend that you use this option after you have either manually budgeted your users, or you have used the previous option first. 
  • Set Projects' Planned Hours as Budgeted: Select this option to make the project Budgeted Hours become identical with the project Planned Hours.  
  • No options available
 

User Name 

The users listed in the Resource Planner belong to the Resource Pools associated with the projects.
For more information about populating Resource Pools with users, see "Working with Resource Pools."
Users could appear listed under the following types of job roles in the Resource Planner:

  • Their primary job role
  • Their secondary job role, in the following scenarios:
    • if the secondary job role has a valid number for the Percentage of FTE Availability in their user profile
    • if the user is assigned to tasks in those roles.

For more information about the Percentage of FTE Availability for a job role, see "Editing User Accounts."

 

"No Role" and "No User" Sections

"No Role" Section

When a user belongs to a Resource Pool associated with a project, but they do not have a job role associated with them, they appear in the No Role section, instead of under a specific job role.

You cannot budget hours for a user in a No Role section. The user must have at least one job role associated with them to be budgeted for work.
no_role_with_user___res_planner.png

"No User" Section

When you assign a task to a team, or you leave it unassigned, the Planned Hours appear under the No User section which appears under the No Role section in the Resource Planner. These tasks do not appear in the Resource Planner when using the View by User view. 

You can see the amount of Planned Hours attributed to tasks on the project in the No User section in the Resource Planner, but you cannot budget for these allocations. 

no_user_and_no_role___res_planner.png

Availability and Allocation of Resources

You can see the availability of your resources and the amount of planned work for your projects in the Resource Planner. These values are displayed in Hours, FTE or Cost amounts and are organized in columns. 
These columns change depending on which view you apply to the Resource Planner:

  • When you apply the View by Project or View by Role views, you can see the following columns:
    • Available Hours, FTE or Cost
    • Planned Hours, FTE or Cost
    • Budgeted Hours, FTE or Cost
    • Hours, FTE or Cost Variance
    • Net Hours, FTE or Cost
  • When you apply the View by User view, you can see the following columns:
    • Available Hours or FTE
    • Planned Hours or FTE
    • Hour or FTE Difference
    • Planned Hours Allocation Percentage 
      NOTE The information is not available as Cost when applying the View by User view to the Resource Planner.

The hours for each column are distributed for the Duration of the tasks on the project.

The Duration of the tasks is the time between the Planned Start and the Planned Completion dates of the tasks. 

For more information about what each column displays, mouse over the name of the column in which the number is displayed.
Net_hours_res_planner_mouse_over.png

For more information about the data displayed in each column, see the "Understanding the Information in the Resource Planner when Budgeting Resources by Hours and FTE" section in "Planning in the Resource Planner."

IMPORTANT If any of the prerequisites required for the correct functionality of the Resource Planner are missing, some of the numbers may be zero, or the Budgeted Hours might be dimmed.
For more information about the prerequisites required for the correct functionality of the Resource Planner, see the "Prerequisites" section in "Planning in the Resource Planner."

Filters

Using filters, you can limit the information that you see in the Resource Planner. You can filter the information displayed in the Resource Planner by the following objects and fields:

  • Portfolio
  • Project Status
  • Team
  • Job Role
  • Resource Pool
    RP_filter_collapsed.png

For more information about filtering in the Resource Planner, see the "Filtering in the Resource Planner" section in "Planning in the Resource Planner."

Settings

By accessing the Settings area, you can enable or disable options to display or hide information in the Resource Planner.

You can enable the Include hours from Issues setting to display Planned Hours from issues in the Resource Planner. This setting is disabled, by default.  

Consider the following when you enable this setting:

  • The name of the user assigned to the issues is displayed under the job role associated with them on the issue and you can specify Budgeted Hours for the user and the job role, for the View by Project and View by Role views.
  • The issues the users are assigned to are listed under the names of the job roles for the View by User view. 

RP_settings_expanded.png

IMPORTANT When the issue Planned Start and Completion dates are outside the timeline of the project, the Planned Hours for the issues do not display in the Resource Planner. 

Full Screen Option (User View Only)

To display the Resource Planner in full screen:

  1. Navigate to the Resource Planner.
  2. Select View by User
    The full screen option is only available for the User View. 
  3. Click the Full Screen icon to view the Resource Planner in full screen.
    RP_sull_sccreen_area_User_View__1_.png
    The Resource Planner expands to occupy your entire browser window. 

Hours/ FTE/ Cost View Selection

The type of information displayed is different depending on which view you apply to the Resource Planner. 

You can select from the following:

  • When you display the Resource Planner in the Role and Project view, the information displays in Hours, FTE or Cost values.
  • When you display the Resource Planner in the User view, the information displays in Hours or FTE values. 
    Hours are displayed by default for all views. (some of the information in this area is also covered in Calculating Costs in the RP - https://workfront.zendesk.com/hc/en-us/articles/115004186433 - update this article also, when changes here occur)

To change the kind of information displayed in the Resource Planner:

  1. Navigate to the Resource Planner.
    For more information about accessing the Resource Planner, see "Accessing the Resource Planner."
  2. Expand the Hours drop-down menu.
    Hours_fte_or_cost_dropdown.png
  3. Select Hours to display availability and allocation information in Hours.
  4. Select FTE to display availability and allocation information in FTE. 
    The information displays in FTE instead of Hours.
    For more information about how the FTE is calculated in the Resource Planner, see "Calculating FTE in the Resource Planner."
  5. (Conditional) If you are viewing the Resource Planner in the View by Project, or View by Role views, select Cost to display availability and allocation information as Cost. The information displays in currency values. Your system administrator defines the system currency. 
    For more information about setting up the system currency in Workfront, see "Setting Up Exchange Rates."
    NOTE You must associate users and job roles with Cost per Hour rates in order to display Cost information in the Resource Planner.
    For more information about associating Cost per Hour rates with job roles, see "Creating and Managing Job Roles."
    For more information about associating Cost per Hour rates with users, see "Editing User Accounts."
    For more information about how Cost is calculated in the Resource Planner, see "Calculating Cost in the Resource Planner."

User Allocation Chart

You can display the Planned Allocation of users against their availability in a chart.

To display the allocation of users in a chart in the Resource Planner:

  1. Navigate to the Resource Planner.
  2. Select View by User.
    NOTE You cannot view the user allocation chart when you select View by Project or View by Role.
  3. Click the user allocation chart icon.
    RP_user_allocation_chart.png
    The following information is displayed:
    • Availability % with no overallocation for all users: this is the amount of time that all users are available for work in a time period, shown as a percentage from their total available time. 
    • Overallocation % for all users: this is the amount of time that users are overallocated in a time period, shown as a percentage from the total available time.
      NOTE An overallocation happens when the Planned Hours are higher than the Available Hours. 
    • Underutilization % for all users: this is the amount of time that users are underutilized in a time period, shown as a percentage from the total available time.
      NOTE Underutilization happens when the Planned Hours are lower than the Available Hours. 
    • There is an overallocation for at least one user during this time period: this indicates that there is an overallocation for at least one user in a time period, although the total amount of time of all users is not overallocated for the time period. 
      You must scroll through the list of users and the hours for the user who is overallocated are highlighted in red. 
      RP__user_allocation_chart_Dec._7__2017.png
  4. (Optional) Click the Overallocation % for all users area in the chart.
    All users that are overallocated are highlighted in red.
  5. (Optional) Click the Underutilization % for all users area in the chart.
    All users that are underutilized are highlighted in blue.
  6. (Optional) Click the indicator that shows where you have at least one user overallocated.
    one_user_overallocation_marker.png
    The users that are overallocated are highlighted in red.  
  7. (Optional) Refresh the page to collapse the chart. 

Export Option

NOTE This option is not enabled for exporting data from the User View in the Preview environment. This limitation is temporary. 

You can export the information in the Resource Planner to an Excel file. You cannot export the information in the Resource Planner in any other file format. 

NOTE You can export data for up to 12 time periods at a time. (this is a temporary limitation for performance - this information duplicates for the resource planner at the business case level)

To export the information in the Resource Planner:

  1. Navigate to the Resource Planner.
    For more information about accessing the Resource Planner, see the "Accessing the Resource Planner" section in "Planning in the Resource Planner."
  2. From the Export drop-down menu, select Excel (.xlsx) to download an Excel file to your computer. 
  3. (Optional) Share the file with another user by attaching it to an email, storing it on a shared drive, or print the file from your Excel application. 

***

ALWAYS READ THESE NOTES FOR 2018 - THERE ARE MODIFICATIONS FOR EACH BETA CAPTURED IN HERE: 

*** This links to Planning in the Resource Planner, Calculating Costs in the Resource Planner, Understanding Project Priority. 

*** Some pink caveats in this article will have to be removed when the performance is corrected and other features are added - later in 2018

*** Take pink out when the 2000 limitation has been lifted after 18.2 - Move this limitation to the Understanding Limitations article as new development is coming to preview in 18.2. 

^^^^^ READ ALL PINK NOTES WITH EVERY PRODUCTION RELEASE AND REMOVE THE CAVEATS FOR PRODUCTION/ PREVIEW.^^^^^

***Inside note: resetUser will not reset the default view for the RP; it is User until the user changes it  and then it returns to the last selected view by the user. 

This article last updated on 2018-04-03 19:47:43 UTC