Must Finish on is a task constraint that can be used when setting tasks on projects.

Features

The Must Finish On (MFO) task constraint schedules a task to finish exactly at the time and date you specify in the Planned Completion Date field. Predecessor relationships will not force the task to be rescheduled. The relationship is essentially ignored.

The task will show as At Risk if predecessor(s) begin to run behind or late.