Follow
Moving an Agile Story

Overview

You can move an agile story to a different iteration, or to the backlog.

Details

  1. Navigate to the iteration that contains the story that you want to move to the backlog.
  2. Click the iteration heading at the top of the page.
  3. Click the Stories tab.
  4. Select the stories that you want to move.
  5. Click More > Move to.
    The Move Story dialog box is displayed.
  6. (Conditional) If you want to move the story to a different iteration, select Another Iteration, then select the iteration where you want to move the story from the dropdown list.
  7. (Conditional) If you want to move the story to the backlog, select team_name's Backlog.
    In the above example, the team name is Development.
  8. Click Move Story.