Follow
Issue Duration

Overview

The Duration of an issue is the planned timeline in which the work item is expected to be active; it is not the actual duration of the issue.

Details

At the issue level, the Duration is the difference between the Planned Completion Date and the Planned Start Date.

Issue duration differs from the duration value at the task level, where duration is manually input and used to calculate either the Planned Completion Date or the Planned Start Date.