Follow
Logging Hours on a Project

You can record and store hours at the project level in Workfront. An overview of information regarding time recorded on a project is also available. 

You can view hours recorded at the Project level as time recorded on a task and as time recorded at the project level. You can also view who submitted the time. 

For more detailed information about logging hours in Workfront, see "Logging Time" in "Recording Time."

To log hours on a project:

  1. Navigate to a project.
  2. Click the Hours tab. (Click More to locate the hours tab if it is not a default tab.)
    All Hours recorded to the project or a task on the project are displayed. 
  3. Click Log Hours. The Log Hours dialog box is opened.
  4. Specify the following information:
    Owner: This field is automatically filled with you name. If you are entering the hours for another user, enter their name.
    Hours: Enter the hours worked.
    Hour Type: Specify whether the hours are project, task, or issue time
    Note: Add a note on the hours, if necessary.
    Screen_Shot_2017-05-03_at_10.16.52_AM.png
  5. Click Log Hours.