Determining Work Breakdown Structure in a Project

***

Defining a Work Breakdown Structure (WBS) for a project is a set of activities that ultimately outlines the scope, objectives, and deliverables of a project. The WBS separates the objectives of the project into manageable work elements, which can be used to define milestones and organize work assignments.

You must have a Plan license with Edit access to Projects to build the Work Breakdown Structure of a project. Additional access to other areas of Workfront might be needed, depending on how many activities you perform while building the WBS. 

We recommend that you keep the project in a Planning status while you make changes to the Work Breakdown Structure, to avoid notifications to trigger to users on the Project Team. 

Defining the Project Objectives and Deliverables

The purpose of a project is to provide tangible deliverables to internal and external stakeholders. The objectives of a project are the goals you want to achieve by completing the project. Objectives are almost always associated with at least one deliverable, and all deliverables should be associated with a project objective.

Project deliverables can be consumer goods, intellectual output (such as reports), or services. For example, if your project scope is to build a house, some of the deliverables may include:

  • creating architectural plans
  • completing plumbing
  • electrical work
  • pouring the foundation
  • framing work
  • closing the sale of the home.

Depending on its size and scope, a project can be made up of multiple objectives with multiple deliverables.

Once you identify your objectives and deliverables, you can begin to break them down into tasks. When defining your tasks you take into account the following parameters: 

  • Amount of time required for completion
  • Required resources needed to complete the work
  • Scheduling of the resources based on the logical timeline of the tasks. 

As you define tasks, ensure that you don't plan too much work for one individual task. If the work required on a task is more than 40 hours (a typical week of work), then you might need to break down that amount of work in subtasks. The completion of all subtasks will then complete the main task. 

To define WBS objectives and deliverables in Workfront, we recommend you perform the following activities to create a hierarchical view of project tasks:

  • If you have not already done so, create a new project.
    For more information about creating a project, see "Creating A New Project."
  • Create tasks for all action items required to complete each objective and deliverable.
    For more information about creating tasks, see "Creating Tasks In A Project." 
  • From the tasks you just created, identify which ones are major objectives and associate them with milestones.
    For more information about creating milestone tasks, see "Creating A Milestone Path" and "Associating A Milestone With A Task."
  • Break down the tasks with too large a scope into subtasks. Associate them with the parent that defines your deliverable or your objective. 
    For more information about creating subtasks, see "Creating Subtasks."
  • Identify dependency relationships between subtasks and between milestones.
    In a dependency relationship, the start of a task is dependent upon the completion of another task or group of tasks.
    For more information about task dependencies, see "Understanding Predecessors," and "Create A Predecessor Relationship On The Task List."
  • Determine if at any point in the lifetime of the project, approvals and reviews are needed. Create approval processes to address this need. 
    For more information about approvals, see "Creating Approval Processes."

Estimating Task Duration and Scheduling Constraints

Once you create the basic milestone and task structure of the project, you can estimate the time it will take to complete the overall project by defining task constraints and durations.

Task constraints define when work on a task must begin or end.  

For more information about defining task constraints, see "Task Constraint Overview."

The Duration of a task is the timeframe available to complete a task. When estimating duration, you may want to enter a value that takes into account the possibility of a delay. If similar projects have been completed in the past, you may have a good idea where to set this value. 

As duration is an estimate, be sure to set optimistic time values to account for factors that might affect the task, such as weather, power outages, supplier difficulties, or other unforeseen events. In addition, be sure to consider whether there are any associated predecessor or dependency tasks and how they may place constraints on work and affect task completion. 

You can modify the duration of a task during the lifetime of a project, but this will also affect the timeline of the project. 

For more information about the Duration of a task, see "Understanding Task Duration and Duration Type Overview." 

Assigning Tasks

After you have defined the duration and constraints of each task, you can determine who has the time and skills to accomplish the work. You can assign tasks to the following entities in Workfront:

  • users.
    Only users with a Plan or Work license can be assigned to tasks. Although you can assign tasks to Requestors and Reviewers, they cannot complete them. For this reason, we do not recommend assigning them tasks. 
    For more information about license types, see "Access Levels by License Type."
  • job roles.
  • teams.

For more information about assigning tasks, see the "Assigning Tasks" section.

Managing Resources

Resource Managing in Workfront allows you to determine whether there is adequate staff to complete the project. When users are added to a project, Workfront shows the utilization of each user. Resource Managers can see the total number of hours the person is assigned to other projects during the time frame of the project.

NOTE As long as the project has a status of Planning, tasks assigned to users do not appear in their task lists.

In the beginning of a fiscal year or quarter, you may want to manage your resources at a higher level, across multiple projects, without the knowledge of a specific Work Breakdown Structure.
For more information about planning the use of your resources at a higher level, see the "Resource Planning" section. 

When you manage your resources in the context of building the Work Breakdown Structure of one project, and ensuring that each task is assigned to the correct resource, you are ready to schedule your resources for the work that needs to be done.
For more information about scheduling your resources, see  the "Scheduling Resources" section. 

Estimating Project Finances

Workfront will calculate the planned costs for each task and the overall costs for a project. Planned costs for a task include all expenses of the task plus the cost of the employee or role assigned to the task. Hourly rates for the task, role, and employee are assigned during task, role, and user creation.

For more information about project finances, see the "Project Finances" section.

Determining Approval Points for the Project

By creating Approval Processes in Workfront, you can establish review points for the project in order to monitor progress and potential problem areas. Through the approval process Project Owners can discern which tasks are late and early, view audit trails that list who changed a task status, and see histories of issues, including how issues were resolved and when they were closed. Upon reviewing a project, Project Owners can determine what steps to take and update the project plan, if necessary.

For more information about approvals, see "Creating Approval Processes."

Viewing Your WBS

Once you complete your WBS, you can view it in a task list. You want to view the following task elements to understand the breakdown of your work:

  • Task sequence and timeline (Planned Start and Completion Dates, and task Duration)
  • Predecessor dependencies
  • Child and parent relationship
  • Assignments

To view the WBS of a project:

  1. Navigate to the project for which you want to see the Work Breakdown Structure.
  2. Select the Tasks tab.
  3. From the View drop-down menu, select one of the following Views:
    • Standard
    • Status
    • Work Breakdown
  4. Ensure that Nothing is selected in the Grouping drop-down menu. The Work Breakdown Structure does not display inside a grouping, unless you also select the Work Breakdown View for your task list. Even when using the Work Breakdown View, the indentation of the tasks is the WBS is not displayed. 

You can also build a task report and apply the Work Breakdown View to the report to see the WBS. 
For more information about building reports, see "Creating a Report."

Saving the WBS of a Project as a Template

If you work on other projects that follow work schedules similar to the WBS you just created, you may want to save the project as a template. A template will save time and effort when creating future related projects. 

If your organization has little turnover, consider waiting until after user assignments are made to save the template. Regardless of when a project is saved as a template, user assignments or specific tasks can be removed during attaching the template to a new project. 

The following elements of a Work Breakdown Structure can be saved in a template, for future use with another project:

  • Predecessor Dependencies
  • Assignments (including Project Owner, Sponsor, and Resource Manager)
  • Approval Processes
  • Task Constraints
  • Documents
  • Expenses and other Financial Information
  • Goals
  • Hour Types
  • Request Queue structure
  • Reminder Notifications
  • Risks
  • Billing Rates
  • Sharing information
  • Custom Forms

For more information about saving projects as templates, see "Saving A Project As A Template."

***