Latest Available Time

Using Latest Available Time

Latest Available Time is a type of task constraint in Workfront. This schedules a task to begin at the latest available time after considering predecessor/successor relationships in the project.

This constraint differs from As Soon As Possible in that it will not force predecessors/successors to be rescheduled. Rather, it will only affect the schedule of the task it is associated with, setting it to the latest available time based on its relationship to other tasks. The value is 'LAT.'

The 'Latest Available Time' constraint type is located under Projects > Project > Task > Task Details > Overview > Edit Overview

Understanding the Difference between Latest Available Time and As Late As Possible

[! This section is duplicated in "As Late As Possible"]The Latest Available Time constraint differs from the As Late As Possible constraint when the following criteria exist:

  • The project is scheduled From Completion
  • Tasks in the project have a predecessor relationship
  • The predecessor task has a flexible task constraint

In this situation:

  • Latest Available Time: Using the Latest Available Time constraint on the successor task gives priority to the predecessor's flexible constraint.
    For example, suppose that Task A is a predecessor to Task B. Task B has the Latest Available Time constraint and Task A has the As Soon As Possible constraint. In this situation, the task is scheduled as close to the start of the project as possible.
  • As Late As Possible: In this scenario, using the As Late As Possible constraint on the successor task gives the priority to the successor task.
    For example, suppose that Task A is a predecessor to Task B. Task B has the As Late As Possible constraint and Task A has the As Soon As Possible constraint. In this situation, the task is scheduled as close to the end of the project as possible.