Follow
Filter: Cross Project Predecessors

This Task filter returns incomplete Cross-Project Predecessors.

To apply this filter:

  1. Navigate to a list of tasks.
  2. From the Filter drop-down menu, select New Filter.
  3. Click Switch to Text Mode.
  4. In the Set Filter Rules for your Report area, paste the following code:
    predecessorsMM:projectID=FIELD:projectID
    predecessorsMM:projectID_Mod=ne
    percentComplete=100
    percentComplete_Mod=ne
  5. Click Save Filter.