Actual Allocation on User Utilization

Actual Allocation on User Utilization will reflect the logged hours which fall within the planned start and completion dates of the task.

For example:

Planned Start Date  -    06/08/2016
Planned End Date    -    06/09/2016

If an hour is logged for 06/08/2016 the system will show Actual Allocation % for the user. However if you log an hour outside the date range (for example, 06/05/2016) the system won't consider it as an Actual Allocation.