Follow
Resource Grid Does Not Show Allocation for Particular Tasks

Problem

When looking at the user allocation on the resource grid, the system doesn't show the allocation for a particular task the user is assigned to.

Solution

Make sure the task in question has both duration and planned hours set. If any of those values is 0, the system won't show allocation for that item. That's because the system takes into consideration both duration and planned hours when calculating allocation for the user.

This article last updated on 2017-11-10 18:25:42 UTC