Dates do not match on project imported from Microsoft Project.

Problem: When importing a project that was exported from Microsoft Project, dates are not matching in Workfront, what they were from MS Project.

Reason: This is caused by how Workfront handles task constraints.

Solution: Go back to Microsoft Project and add predecessors to the tasks, this will let Workfront know how to handle the task start dates, and should better align with what is in Microsoft Project.