Capacity Planner Limit

Capacity Planner and Resource Estimate Limit

 

Currently, the Resource Estimates in the Project Details->Business Case as well as the Capacity Planner in People->Resource Planning->Resource Pools have a limit of displaying data of 1095 total days which is equal to 3 years including weekends. So, for example, if you have a Project with the Planned Start Date in 1/1/2015 and Planned Completion Date in 1/1/2020 the allocation for it will appear until 1/1/2018.