Follow
Column: Show Names of Parent Tasks in All Caps

You can add this column to a task view to display the name of the parent tasks in all capital letters.

view_task_with_all_caps_parent.PNG

To build this column in a task view:

  1. Navigate to a list of tasks.
  2. From the View drop-down menu, select Customize View.
    Or
    From the View drop-down menu, select New View
  3. In the Column Preview area, click the header of the column that shows the task name in the list.
  4. Click Switch to Text Mode.
  5. Mouse over the text mode area, and click Click to edit text.
  6. Remove the text you find in the Text Mode box, and replace it with the following code:

    descriptionkey=name
    displayname=Task Name
    textmode=true
    valueexpression=IF({numberOfChildren}>"0",UPPER({name}),{name})
    valueformat=HTML
    width=150

  7. Click Save View.

 